Turkish power ship proposed for Adelaide
via Tallbloke’s Talkshop
http://ift.tt/1WIzElD
The dash for renewables in South Australia has gone so badly wrong that crisis measures are now called for, as PEI reports.
A large-scale temporary power solution is being considered, as South Australia struggles to ensure its energy security.
A 250 MW ship-based power station is under consideration as a solution to the crisis for the Australian state, which has seen a lot of investment in renewable power over recent years, while old fossil stations were retired.
The Turkish ship could be operational by the end of the year for less than the $360m budgeted for a new state-owned gas-fired power plant of the same capacity.
The ship-based plant would plug into the high-voltage grid near the 479 MW Pelican Point power station, which returns to full capacity on July 1.
A second option would be for a 125 MW Powership at Outer Harbor and another of the same size anchored off Port Augusta, plugging into the grid near the site of the defunct Northern power station.
The Powership fleet can operate on natural gas, liquid natural gas or heavy fuel oil and it is likely the ship would be leased until a permanent plant was built.
. . .
Adelaide Now online reports that opposition politicians are critical of the move, saying that using such ships, typically sent to war ravaged regions, shows the government’s poor decision making on power policy, linking it to the increase in residential electricity bills.
Full report: Turkish power ship proposed for Adelaide – Power Engineering International
via Tallbloke’s Talkshop http://ift.tt/1WIzElD
June 26, 2017 at 12:45PM