Hornsea Offshore Wind Farm Opens–At Huge Cost To Energy Customers

By Paul Homewood

 

 

h/t Dennis Ambler

The far left Yale Environment 360 puff up the opening of the heavily subsidised Hornsea offshore wind farm:

 image

The world’s largest offshore wind farm began operations this week in the North Sea. According to Earther, the first 50 turbines at the Hornsea One wind farm, located 75 miles off the east coast of Yorkshire in the United Kingdom, are now generating electricity for up to 287,00 homes.

When completed in 2020, the wind farm, operated by Ørsted, will have 174 turbines with a total capacity of 1.2 gigawatts (GW), enough to power 1 million homes. The facility — which will send electricity to the UK, Netherlands, Belgium, Germany, and Scandinavia — will have more than twice the capacity of the current largest offshore operation, also in the UK.

Because of its distance from shore, teams of workers will live at sea for two weeks at a time maintaining the wind farm. “Operating a wind farm this far offshore is unprecedented,” David Coussens, deputy operations manager for Hornsea One, told Offshore Wind, a trade publication. “We’ve had to think creatively and come up with new ways of working to overcome the logistical and technical challenges of operating a massive power station 120km [75 miles] from the shore.”

The UK currently has 8.2 GW of offshore wind capacity, representing 44 percent of Europe’s entire offshore wind production. The country aims to double its capacity by 2030, and is planning to build an equally large wind farm next to Hornsea One. The United States, in comparison, has just 30 megawatts of offshore wind capacity, Earther reported.

https://e360.yale.edu/digest/worlds-largest-offshore-wind-farm-now-operational

What our leftie friends forgot to mention is that Hornsea is going to be heavily subsidised for the next fifteen years.

This year it will receive a guaranteed payment of £158.75/MWh for every unit of electricity it can produce, compared to the current market price of £45/MWh:

 image

https://www.lowcarboncontracts.uk/cfds/hornsea-phase-1

Hornsea’s total capacity of 1.2GW, due on stream in the next two year, can expect to receive annual subsidies of £430m for the next fifteen years, all index linked, and all on top of the revenue for the electricity they actually sell.

It’s certainly a good deal for someone, but not the poor suffering consumers who will end up footing the bill.

via NOT A LOT OF PEOPLE KNOW THAT

http://bit.ly/2IllZh8

June 6, 2019 at 03:46AM

One thought on “Hornsea Offshore Wind Farm Opens–At Huge Cost To Energy Customers”

Leave a comment