Carbon Capture fails again: Chevron spends $600 a ton to bury fertilizer under the NW Shelf

Stuffing a useful gas into holes under the ocean is harder than they thought

Chevron spent $3 billion to put just 5 million tons of carbon dioxide under the ocean floor. The project was plagued with delays and problems with sand clogging the machinery. They captured about one fiftyth of the Chevron emissions in a five year period.

CCS is a modern industrial talisman:

Chevron concedes CCS failures at Gorgon, seeks deal with WA regulators

Reneweconomy

Chevron is understood to have spent more than $3 billion building the carbon capture facility, but it took several years after the start of gas production for the Gorgon CCS project even to begin operation due to delays and technical difficulties. The first CO2 was injected into an undersea deposit in 2019.

It is understood regulators may ask Chevron to offset the emissions it failed to store by purchasing offsets from either local or international carbon markets. If Chevron is made to buy Australian Carbon Credit Units, which currently trade at above $20 per tonne, the cost to the company could easily exceed $200 million.

So they could have done it all 30 times cheaper. (Or, if they […]

via JoNova

https://ift.tt/3BFiIUP

July 24, 2021 at 11:05PM

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s