By Paul Homewood
h/t Robin Guenier
Billions of pounds’ worth of green energy projects are on hold because they cannot plug into the UK’s electricity system, BBC research shows.
Some new solar and wind sites are waiting up to 10 to 15 years to be connected because of a lack of capacity in the system – known as the "grid".
Renewable energy companies worry it could threaten UK climate targets.
National Grid, which manages the system, acknowledges the problem but says fundamental reform is needed.
The UK currently has a 2035 target for 100% of its electricity to be produced without carbon emissions.
But meeting the target will require a big increase in the number of renewable projects across the country. It is estimated as much as five times more solar and four times as much wind is needed.
The government and private investors have spent £198bn on renewable power infrastructure since 2010. But now energy companies are warning that significant delays to connect their green energy projects to the system will threaten their ability to bring more green power online.
A new wind farm or solar site can only start supplying energy to people’s homes once it has been plugged into the grid.
Energy companies like Octopus Energy, one of Europe’s largest investors in renewable energy, say they have been told by National Grid that they need to wait up to 15 years for some connections – far beyond the government’s 2035 target.
https://www.bbc.co.uk/news/science-environment-65500339
Somebody, of course, has to pay for all of this nonsense, something Justin Rowlatt forgets to mention.
Maybe if all of these renewable schemes had to pay the cost themselves, they might get the work done quicker.
via NOT A LOT OF PEOPLE KNOW THAT
May 12, 2023 at 03:29AM